00:02 Things are chugging along nicely at this point. 00:04 We have a work breakdown structure and activity list. 00:08 We've got an estimation of their durations and we stuck some buffers on to cover our backs. Wow. 00:13 Way to go. But things do look a bit like an activity soup right now. 00:19 We need to jumble this mess and see how activities link with each other. 00:24 In other words, we need to understand their dependencies. 00:28 It's not hard to imagine how some tasks are dependent on others. 00:33 You can't have the cars delivered without a showroom, and you can't build your showroom until you've started digging. 00:39 And you can't start digging until you have the machinery on site. 00:43 You can, however, start recruiting the sales team. 00:47 So let's look at the four main reasons why dependencies exist between tasks. First logical dependency. This is just like what I described. 01:01 You can't put windows in your showroom until you've built walls. 01:06 Second, we've got resource constraints. 01:09 Lack of resources can affect the sequencing of tasks. 01:13 Let's say you have to work packages as part of your showroom project. 01:17 One for performing a financial comparison between two potential interior designers and another for preparing a detailed report on travel expenses. 01:26 But you only have one business analyst and nobody else qualified to perform the tasks. The two tasks cannot be completed simultaneously. 01:35 Therefore, your business analyst has to finish one before they can start the other. 01:42 Third, we have external dependencies. 01:45 These can be anything from building work that needs to be signed off by the city to paint work that can only be done in good weather. 01:53 You get it. The activities that are affected by external sources. 01:59 The fourth are called soft dependencies. 02:02 These are applied by the project manager themselves and could include things like a task not going forward unless the project manager has checked the previous task. 02:11 They are called soft dependencies as they are easily amendable due to the fact that the project manager set them in the first place. 02:19 Now let's have a look at the types of dependencies. 02:23 For again, is the magic number here. 02:29 First we have finish to start, where the second task cannot start until the first has finished. 02:37 The task paint. 02:39 The whole room cannot start until you finish the task by paint. 02:45 Second there is finish to finish where the second task cannot be finished until the first has been finished. 02:52 The task, paint the whole room cannot be finished before task paint the fourth wall is fully finished. 03:00 Third is start to start where the second task can only start when the first starts the task paint. 03:07 The whole room must start. 03:09 So the task paint, the first wall can also start. 03:14 And lastly the not as common. 03:16 Start to finish where the second task has to start before the first can finish. 03:23 Let's step away from the painting. 03:25 Examples for this one and imagine the construction site needs 24 hour security. Guard two's shift must start before Guard one's shift can finish. 03:36 This way there will be no interruption in the surveillance for any thieves to sneak in. 03:43 As always, the project manager must take all these factors into consideration because any missed dependencies are sure to cause delays and increase costs. 03:52 Once the project manager has worked out the dependencies, we can apply the critical path method. We came across a couple of lessons ago to potentially find out the shortest time in which we can complete the project. 04:04 So let's look at this next.
The lecture Identifying Dependencies by 365 Careers is from the course Project Phase: Planning (EN).
5 Stars |
|
5 |
4 Stars |
|
0 |
3 Stars |
|
0 |
2 Stars |
|
0 |
1 Star |
|
0 |